# Data centre land offers in Ireland: what to check before you sign

*Published 2026-11-23 by FarmAI Ireland*

If you are approached about a data centre in Ireland, the offer may be for solar ground, not a server hall. Since December 2025, new data centres must supply their own generation and source 80% of their power from new Irish renewables. Three papers come before any lease or sale, and only some bind you. Tax on the money differs from farming. Checked 23 November 2026.

## Why would a data centre want farmland in Ireland?

A Georgia cattleman told [Fortune](https://fortune.com/2026/11/22/meet-fouth-generation-cattleman-will-harris-cattle-cycle-broken/) on 22 November that investors and developers now outbid farmers for land. "The land is moving out of the hands of the farmer," he said. That is America. Here is the Irish version.

Data centres used 23% of Ireland's metered electricity in 2025. That is the [CSO's figure](https://www.cso.ie/en/releasesandpublications/ep/p-dcmec/datacentresmeteredelectricityconsumption2025/keyfindings/): 7,663 GWh, up 10% in a year. All the homes in the country used 28%.

The regulator says the grid has limits. In December 2025 the energy regulator, the CRU, [set new connection rules](https://www.cru.ie/about-us/news/the-cru-publishes-its-decision-on-new-electricity-connection-policy-for-data-centres/). Three of them matter to a landowner.

1. **Own generation.** A new data centre must provide generation or storage, on site or nearby, to match its maximum demand.
2. **New renewables.** It must meet at least 80% of its yearly demand from additional renewable projects in the Republic. It gets six years to build up to that.
3. **Location.** EirGrid and ESB Networks must judge each application on where it sits on the network.

Read those together. A data centre now comes with a power project attached, and solar needs ground. The renewables can be anywhere in the Republic, so the knock on the door need not be near Dublin. Teagasc puts solar at [about two hectares per megawatt](https://teagasc.ie/news--events/daily/is-it-viable-to-let-land-for-solar-projects/).

One project shows the shape. In June 2026, Westmeath County Council [granted a ten-year permission](https://www.rte.ie/news/business/2026/0608/1577376-westmeath-data-centre-approved/) for a six-unit data centre and energy project near Rochfortbridge. The site is 600 acres, with a solar farm on tillage ground. [Ten appeals](https://www.thejournal.ie/westmeath-data-centre-stalled-7094643-Jul2026/) went to An Coimisiún Pleanála. We found no published decision when we checked on 23 November 2026.

## What will you actually be asked to sign?

No Irish body has published a farmer's guide to data centre land deals. The nearest is Teagasc's solar guidance, and the deal structure is the same family. Its [legal note](https://teagasc.ie/wp-content/uploads/2025/05/Solar-PV-Legal-Issues.pdf), written with two solicitors in 2016, sets out the usual order.

1. **Exclusivity agreement.** A short document with a map. You agree to stop talking to anyone else for a set period.
2. **Heads of Terms.** The outline of the deal: option period, lease term, fees, who insures what. Teagasc says these are not contractually binding.
3. **Option agreement.** This one binds you. You get a non-refundable fee. The developer gets time to seek planning and a grid connection, and the right to walk away.
4. **Lease or sale.** The developer decides when to trigger it. The terms were fixed back when you signed the option.

Teagasc's own words on step three: an option "usually favours a developer rather than a landowner". It also advises you to avoid exclusivity until the full Heads of Terms are agreed.

The length is the part to sit with. Teagasc says solar leases run 25 years or more. One Westmeath farmer told the [Irish Farmers Journal](https://www.farmersjournal.ie/amp/life/features/farmers-fight-to-save-tillage-land-from-data-centre-development-921473) he was offered a 35-year minimum. He turned it down, with four young children in mind.

## What changes on tax if you sell or lease?

This is where a good offer can shrink. These are Revenue's published positions. Your own case needs an adviser.

**Selling.** Revenue charges [33% on gains from development land](https://www.revenue.ie/en/gains-gifts-and-inheritance/transfering-an-asset/how-to-calculate-cgt.aspx). Most other gains have been charged at 31% since 7 October 2026. Whether your sale counts as development land is a question for your tax adviser.

**Retirement relief.** If you are 55 or over, you may get relief on selling farm assets you have [owned and used for ten years](https://www.revenue.ie/en/tax-professionals/tdm/income-tax-capital-gains-tax-corporation-tax/part-19/19-06-03.pdf). Outside the family, [full relief stops](https://www.revenue.ie/en/gains-gifts-and-inheritance/cgt-reliefs/disposal-of-a-business-or-farm.aspx) at a market value of €750,000. It drops to €500,000 from age 70. Both are lifetime limits.

**Land you were given or inherited.** Agricultural relief cuts the taxable value of a farm gift by 90%. Revenue can [claw it back](https://www.revenue.ie/en/gains-gifts-and-inheritance/cat-reliefs/agricultural-relief/can-agricultural-relief-be-withdrawn-or-clawed-back.aspx) if you dispose of the land within six years. The way out is to put the proceeds into other agricultural property within one year.

**Leasing for solar.** Teagasc says lease and option income is fully taxed. It does not get farming tax relief. For the next generation, Revenue [counts land under panels as agricultural property](https://www.revenue.ie/en/gains-gifts-and-inheritance/cat-reliefs/agricultural-relief/what-is-agricultural-property.aspx) only up to half the land in the gift. That page makes no such allowance for a data centre building.

If the ground is already zoned and serviced, a separate annual charge may apply. Our piece on the [zoned land tax on Irish farmland](/read/residential-zoned-land-tax-irish-farmland) covers that.

## What does it cost you, and what might it pay?

It should cost you nothing up front. Teagasc's advice is that the developer covers your legal and professional fees, whether or not the project goes ahead. Get that in writing before your solicitor opens a file.

On income, Teagasc's solar guidance, published in July 2025, put rents at €2,200 to €3,500 per hectare per year. It said €2,200 to €3,000 was more common. Treat that as a dated benchmark for solar ground, not a quote.

We found no Irish source for data centre site prices. So we are not printing one.

## What to ask before you sign anything

Teagasc's questions for a solar developer fit here too.

- Who are they, and how many sites have they built?
- Who will own and run the project, or will it be sold on?
- Who pays for decommissioning and reinstatement, and is there a bond behind it?
- What happens to drainage and soil during construction?

Add four of your own.

- Does your bank hold a charge on the land? Teagasc says you need its consent before a lease.
- Can you still transfer the farm? Option agreements usually make that subject to the developer's consent.
- What happens to your [BISS](/schemes/biss) entitlements and any ACRES contract on that ground?
- Where does this leave your [succession plan](/read/farm-succession-planning-ai)?

## Frequently asked questions

### **Is a Heads of Terms binding in Ireland?**

Teagasc's legal guidance says Heads of Terms are not contractually binding. They usually carry a confidentiality clause and sometimes an exclusivity one. The option agreement that follows is the binding document. Have a solicitor read both before you sign either.

### **How much capital gains tax is due on land sold for development in Ireland?**

Revenue lists a 33% rate for gains from development land. Most other gains are charged at 31% since 7 October 2026. Retirement relief may reduce the bill if you are 55 or over, with lifetime limits of €750,000 or €500,000.

### **Can you still claim agricultural relief on land leased for solar?**

Revenue treats land under solar panels as agricultural property only where the panels cover no more than half the land in the gift or inheritance. Above that, the relief is at risk. Talk to a tax adviser before signing if a transfer is planned.

## Where to get help

Start with three people: a solicitor who has handled option agreements, a tax adviser, and your Teagasc advisor. Teagasc's solar guidance is free and worth reading first, even if the offer says data centre on it.

For the planning side, your county council holds the zoning maps and the planning file. Anyone can read a planning application, including one beside you.

## The bottom line

The price on the first page is the easy part. Before you sign an exclusivity letter, ask the developer to cover your solicitor and tax adviser. Then let those two tell you what the offer is worth after tax, after 25 years, and after the farm passes on.

---

## Sources

- [CRU: Decision on new electricity connection policy for data centres (12 December 2025)](https://www.cru.ie/about-us/news/the-cru-publishes-its-decision-on-new-electricity-connection-policy-for-data-centres/) — Source of the generation requirement, the 80% renewable rule, the six-year glide path, the location test and the 22% to 31% demand forecast
- [CSO: Data Centres Metered Electricity Consumption 2025, key findings](https://www.cso.ie/en/releasesandpublications/ep/p-dcmec/datacentresmeteredelectricityconsumption2025/keyfindings/) — Source of the 23% share of metered electricity in 2025, the 7,663 GWh total and the 10% annual rise
- [Teagasc: Is it viable to let land for solar projects?](https://teagasc.ie/news--events/daily/is-it-viable-to-let-land-for-solar-projects/) — Source of the option period, lease length, rent range, the questions to ask a developer, and the tax treatment of lease and option income
- [Teagasc: Solar PV legal issues, 2016 (exclusivity, Heads of Terms, option and lease)](https://teagasc.ie/wp-content/uploads/2025/05/Solar-PV-Legal-Issues.pdf) — Source of the order of the paperwork, which documents bind you, bank consent, and the developer's consent to a land transfer
- [Revenue: How to calculate CGT](https://www.revenue.ie/en/gains-gifts-and-inheritance/transfering-an-asset/how-to-calculate-cgt.aspx) — Source of the 33% rate on development land gains and the 31% rate on most other gains from 7 October 2026
- [Revenue: Retirement Relief on disposal of a business or farm](https://www.revenue.ie/en/gains-gifts-and-inheritance/cgt-reliefs/disposal-of-a-business-or-farm.aspx) — Source of the age 55 rule and the €750,000 and €500,000 lifetime limits for disposals outside the family
- [Revenue: Tax and Duty Manual Part 19-06-03, disposals of business or farm on retirement](https://www.revenue.ie/en/tax-professionals/tdm/income-tax-capital-gains-tax-corporation-tax/part-19/19-06-03.pdf) — Source of the ten-year ownership and use condition for qualifying assets. Last updated August 2026
- [Revenue: Can Agricultural Relief be withdrawn or clawed back?](https://www.revenue.ie/en/gains-gifts-and-inheritance/cat-reliefs/agricultural-relief/can-agricultural-relief-be-withdrawn-or-clawed-back.aspx) — Source of the six-year clawback on disposal and the one-year window to reinvest
- [Revenue: What is agricultural property?](https://www.revenue.ie/en/gains-gifts-and-inheritance/cat-reliefs/agricultural-relief/what-is-agricultural-property.aspx) — Source of the rule that land under solar panels counts as agricultural property only up to half the land in the gift or inheritance
- [Irish Farmers Journal: Farmers fight to save tillage land from data centre development (1 July 2026)](https://www.farmersjournal.ie/amp/life/features/farmers-fight-to-save-tillage-land-from-data-centre-development-921473) — Report on the Rochfortbridge appeal, including a farmer's account of a solar lease offer and a 35-year minimum term
- [RTÉ News: Westmeath council green light for €1bn data campus (8 June 2026)](https://www.rte.ie/news/business/2026/0608/1577376-westmeath-data-centre-approved/) — Report of the ten-year permission for a six-unit data centre and energy project on a 600-acre site
- [TheJournal.ie: Westmeath data centre plans stalled after 10 appeals (7 July 2026)](https://www.thejournal.ie/westmeath-data-centre-stalled-7094643-Jul2026/) — Report of ten third-party appeals lodged with An Coimisiún Pleanála
- [Fortune: This cattleman's farm brings in $30 million a year (22 November 2026)](https://fortune.com/2026/11/22/meet-fouth-generation-cattleman-will-harris-cattle-cycle-broken/) — The US report that prompted this piece: land moving from cattle producers to investors and data centre developers

---

*Source: [FarmAI Ireland](https://farmai.ie/read/data-centre-land-offer-ireland-what-to-check)*